Project Progress

Real-time construction milestones and phase updates for One Finserv Campus, Pune.

Last updated: May 2025
68%
Overall Complete
34%
In Progress
18%
Delayed
14%
Not Started

Construction Phases

Seven phases from foundation to commissioning — each tracked independently.

PhaseNameStatusProgress
1Foundation & BasementCompleted
100%
2Structural FrameworkCompleted
100%
3Facade & ExteriorIn Progress
72%
4MEP (Mechanical, Electrical, Plumbing)In Progress
55%
5Interior Fit-outIn Progress
38%
6Landscaping & AmenitiesNot Started
0%
7Safety & CommissioningNot Started
0%

Recent Updates

Latest site activity and construction milestones.

Structural20 May 2025

Tower C Structural Topping Out

Tower C reached its final structural floor, completing the primary framework for all four campus towers ahead of schedule.

Facade18 May 2025

Curtain Wall Installation Milestone

Over 65% of the glass curtain wall panels have been installed on the north and east elevations of Tower A.

Interior15 May 2025

Interior Fit-out Commenced on Floors 2–5

Interior partitioning, flooring, and ceiling works have commenced across floors 2 to 5 of Tower A, with MEP rough-in underway.

Progress10 May 2025

Overall Completion Reaches 68%

The monthly independent progress audit confirmed overall project completion at 68%, maintaining the on-track status for the 2026 delivery.